Project: York House, Kensington Church Street, Kensington, Greater London
Duration of Project: 30 Weeks
Completion date: November 2007
Scope of Works:
Nebulas Water Cleaning to Brick and stone
Detailed Shedule of works required
Restoration of Stonework
Structural repairs
Restoration of Brickwork
New Stone
Brick/Stone Re-pointing
York house In Kensington Church Street Project requires careful structuring of the work force to complete the works on a very tight time period.
FM Restoration are scheduled to complete on time.
|